Decommissioning Liquid-Cooled AI Racks: How to Drain, Dispose and Document

Guide To Liquid Cooling Decommissioning And Retirement
Reading Time: 7 minutes

Most GPU decommissioning playbooks were written for gear you unplug and roll out. What happens when they’re high-density direct-to-chip (D2C) racks?

A liquid-cooled rack adds a drain sequence, a fluid you must identify before you can legally dispose of it, and paperwork that belongs next to your certificates of destruction. Miss any of it in planning and you pay on site in schedule slips, spills, or a compliance gap you didn’t know you had.

 

Fast Facts: What You Need To Know About Decommissioning Liquid Cooled IT Gear

    • Liquid cooling is expected to reach about 53% of high-end AI infrastructure in 2026, up from roughly 33% in 2025 (TrendForce).

    • The cooling loop must be isolated and drained before de-racking starts, and OCP guidance uses compressed dry air below 75 psi to push residual fluid under 5%.

    • Most direct-to-chip loops run PG25 (75% water, 25% propylene glycol), which contains no PFAS itself. Check the SDS for additives. 

    • Immersion systems use dielectric fluids that can contain PFAS and follow a different disposal path.

    • Drain logs, waste determinations, and disposal records belong in the same chain-of-custody file as your data destruction records.

    • A GPU tray that’s drained, dried and documented keeps its resale value. A half-drained one invites corrosion, which cuts into that value.

 

Why Liquid-Cooled Racks Are Reaching Retirement Now

TrendForce projects liquid cooling in high-end AI infrastructure will climb from about 33% in 2025 to 53% in 2026. 

Heat density forced the change. HPE lists a nominal 132 kW per GB200 NVL72 rack, with peak draw around 192 kW compared with 8-12 kW for a typical air-cooled rack. 

Those figures track what’s going into data halls. With IT equipment commonly refreshed every three to five years, that puts the first big wave of liquid-cooled racks on decommission schedules right now. 

 

Decommissioning A Liquid-Cooled GPU Rack Starts With Plumbing

On an air-cooled rack, removal starts once power is off and cables are labeled. On a liquid-cooled rack, removal waits on the technology cooling system (TCS), which is the loop running from the coolant distribution unit (CDU) through the rack manifold to every cold plate. Technicians need to isolate that system from facility water and drain it.

The steps to perform a drain procedure are well documented. The Open Compute Project’s March 2026 guidance on shipping and storing cold plate hardware, written by engineers from Meta and NVIDIA, describes purging assemblies with compressed clean dry air below 75 psi for several minutes to bring residual fluid under 5%. It defines “dry” hardware as under 10% coolant by volume and says to release purge pressure before transport.

Weight is the second change. A fully loaded GB200 NVL72 rack at about 3,245 pounds, per HPE’s spec sheet, calls for rated lift equipment and a floor-loading check along the entire exit path, from the rack position to the dock.

Operators close and tag the valves on the facility side, then the rack side gets drained and purged. Only then does anyone break a connection or pull a tray. 

 

Who Owns What in a Colocation Facility

In colocation, most delays come from one unanswered question: who drains what? Settle it in writing before the project starts. A typical split looks like this:

  • Facility water loop and chillers: owned by the colocation provider and left running.
  • Coolant distribution unit (CDU): usually the provider’s. In-rack CDUs are often the tenant’s. Whoever owns it isolates it.
  • Row manifold or technology cooling system: varies the most. Agree in writing who isolates and drains it.
  • Rack manifold, hoses, quick-disconnects and cold plates: the tenant’s, drained by the tenant or its decommissioning partner.
  • Coolant in the tenant-side loop: usually the tenant’s. Agree in writing who the waste generator is and who signs the waste determination.

Contracts vary, so treat this as a starting point and confirm against your colocation agreement.

 

Drain-and-cap sequence for a cold plate rack

 

  1. Confirm the coolant and volumes. Pull the SDS, estimate loop volume, and book the waste hauler or glycol recycler before the drain date.
  2. Agree on the ownership boundary in writing (see “Who Owns What in a Colocation Facility” above), including who signs the waste determination.
  3. Power down the IT load and let the loop return to room temperature.
  4. Close, lock out and tag the isolation valves at the CDU or row manifold. Photograph the tags.
  5. Drain the rack-side loop into labeled, closed containers. Keep drip trays and absorbent pads under every quick-disconnect, and leave leak detection on.
  6. Purge with clean dry air below 75 psi for several minutes, until residual coolant is under about 5% (OCP, March 2026).
  7. Disconnect and cap every port.
  8. Choose the final state: ship dry (under 10% coolant by volume), or charge with nitrogen at 25–50 psi for storage, which typically holds for 3–12 months. Avoid partly drained storage, which invites corrosion.
  9. Check the lift and floor path. A fully loaded GB200 NVL72 rack weighs about 3,245 lb.
  10. Log it all in the rack’s audit file (checklist below) before the rack leaves the floor.

This is a general outline. Always follow the equipment manufacturer’s procedures and your site’s safety requirements.

 

Your Disposal Path Depends On Which Fluid You’re Using

Single-phase direct-to-chip cooling holds about 55% of the liquid cooling market in 2026, according to Schneider Electric, and it typically runs PG25. At a 25% concentration, propylene glycol makes the mix biostatic, which slows bacterial growth on cold plate fins spaced around 50 microns apart. It is also far less toxic than ethylene glycol, which is why OCP recommends it.

Coolant Disposal Paths:

The coolant in the loop decides the disposal path. The three you’re most likely to find:

PG25 (25% propylene glycol, 75% water). The standard coolant in single-phase direct-to-chip systems. Propylene glycol and water are not PFAS, but check the SDS for the inhibitor package. Send it to a glycol recycler or licensed waste hauler, and don’t pour it down a drain unless your local wastewater authority allows it. Keep the drain log, the waste determination, and the shipping paperwork or recycling receipt.

Hydrocarbon dielectric fluids (synthetic or mineral oils). Common in single-phase immersion. They’re generally PFAS-free, but confirm on the SDS. Depending on condition, they can often be filtered and reused, or sent to a recycler that accepts them. Keep the SDS, the volume recovered, and the reclaim or recycling receipt.

Fluorinated dielectric fluids (fluorocarbons). Used in two-phase immersion and some single-phase systems. Many are classed as PFAS. They evaporate easily, so keep containers sealed. Send them to a specialist reclaimer, or back through the fluid supplier if it offers a take-back program. Keep the SDS, the volume recovered, the chain of custody to the reclaimer, and a note of whether any state PFAS rules apply.

This is general guidance. Your environmental, health and safety (EHS) team and the fluid’s SDS decide the final path.

Immersion systems come with different considerations. Immersion tanks use dielectric fluids, and two-phase systems have historically relied on fluorocarbon fluids containing PFAS, including 3M’s Novec line. 3M announced in 2022 that it would exit PFAS manufacturing by the end of 2025. EPA’s TSCA section 8(a)(7) PFAS reporting period now opens no later than January 31, 2027, after several postponements (UL Summary) and several states have their own PFAS reporting rules so check yours.

Identify the fluid from the safety data sheet and system documentation before the drain date. PG25 from a cold plate loop and a fluorocarbon from a two-phase tank leave your building on completely different paperwork. 

Immersion retirement works differently, and it depends on the type of tank. In single-phase immersion, which uses oils that don’t evaporate, servers are lifted out and left to drip over the tank. Oil works its way into slots, connectors and under labels, so a wipe-down usually isn’t enough for resale. Plan for a more thorough cleaning step, such as a dielectric solvent wash. In two-phase immersion, the fluid evaporates quickly once hardware leaves the tank, so the hardware comes out nearly dry and the focus shifts to keeping fluid loss to a minimum. Either way, immersion fluids are expensive, so recovered fluid can often be filtered and reused rather than discarded. Buyers inspect immersion-run hardware more closely, so keep cleaning records in the audit file.

 

GPU Rack Coolant Disposal Needs Its Own Chain of Custody

Quick-disconnect fittings still leak a little. Schneider’s thermal engineers note that QDs often give a slightly wetted disconnect instead of a fully dry break, which is part of why the industry settled on low-toxicity PG25. Across a row of racks those drops add up, so keep drip trays, absorbent pads, and leak detection active until the last hose comes off.

Used coolant is not automatically hazardous waste. The EPA’s position is that glycol coolant isn’t a listed hazardous waste, so it only has to be managed as one if it shows a hazardous characteristic, typically confirmed with a Toxicity Characteristic Leaching Procedure (TCLP) test. Whoever drains it has to make and document that determination, states can regulate it more strictly, and pouring it down a floor drain isn’t an option without approval from the local wastewater authority.

Coolant disposal is governed by RCRA and your state environmental agency, so ask any decommissioning vendor how they handle it and who hauls it.

Your audit file needs the same rigor you already demand for drives, keep one per rack:

Close-Out Audit File: One per Rack

      • Rack ID, asset tags and serial numbers of all trays
      • Coolant SDS and coolant type
      • Photos of tagged isolation valves before the drain
      • Drain log: date, technician, volume recovered
      • Purge record: pressure, duration, residual check
      • Final state: dry, or nitrogen-charged (pressure and date)
      • Waste determination (TCLP results or generator knowledge, signed)
      • Hauler manifest or recycling receipt for the coolant
      • Freight bill of lading and temperature mode
      • Data sanitization certificates for every drive
      • Final disposition per serial: redeployed, resold, harvested or recycled

 

Plan Your Cooling Exit Strategy In Advance

Drain-and-cap work belongs in the project plan on day one, next to asset inventory and data sanitization, because it controls crew skills, lift rentals, freight mode, and the order racks leave the floor. A full decommissioning project plan should name who isolates facility water, who drains the rack side, which fluid sits in each loop, and where every drum goes.

Freight requires its own line item. OCP’s guidance puts standard road freight between -20°C and 45°C; any PG25 left in the hardware can thicken or freeze in cold weather, so winter shipments may need temperature-controlled freight.

Liquid cooling changes how the hardware comes out of the rack. A retired GPU’s value still comes down to model, condition, test results, and what the secondary market is paying at the time. The exception is a tray that was partly drained or stored wet. Residual coolant can corrode cold plates and connectors, and corrosion is exactly the kind of condition issue that lowers what a buyer will pay.

The one place a coolant loop can still cost you money is the warehouse. OCP flags hardware left partially drained as a high corrosion risk that isn’t suited to long-term storage, while fully dried assemblies charged with nitrogen at 25 to 50 psi typically hold for 3 to 12 months. Once your trays are dry and documented, see what your retired GPUs are worth.

Draining adds steps to retirement, but the goal hasn’t changed. Racks that leave dry and documented keep their resale and redeployment value, stay out of the waste stream longer, and give sustainability and audit teams records they can rely on. Plan the drain the day you plan the refresh, not the week before the trucks arrive.

Planning a refresh or shutdown?

Decommission your data center without the risk.

exIT Technologies handles the removal, secure data destruction, resale, and recycling of your retired equipment, so you recover value while staying compliant.

Explore Data Center Decommissioning →
en_USEnglish